Perch Lake Road Project
The Town of St. Joseph is planning to rehabilitate and widen Perch Lake Road from 53rd Street to 60th Street in the spring/summer of 2021. In general, the project consists of the following:
- Pulverize the existing pavement and base
- Widen the roadway to a total width of 24’ of pavement
- Construct 2’ wide gravel shoulders
- Regrade ditches
- Replace select culverts
Please contact Kellie Schlegel or Lee Mann (Town Engineer) at the information below if you have any questions or concerns regarding this project, or to provide your contact information. Please note that additional information will be sent out next spring 2021 with more details regarding the construction process, resident access, mail delivery, etc.
You can also contact the Town Chair, Theresa Johnson, at 715-222-6235, or any of the Town Supervisors with your questions or comments.
Lee Mann – Town Engineer (Stantec)
651-775-5956
Kellie Schlegel – Design Engineer (Stantec)
651-775-5622
Click Here for a Project Map
Click Here for information provided to adjacent property owners
Click Here to Submit Comments
Project Schedule
Design | In Progress |
Town Board Authorizes Project Bidding | December 10, 2020 |
Advertisement for Bids Published | January 14, 2021 |
Bid Opening | February 4, 2021 |
Town Board Considers Project Award | February 11, 2021 |
Construction Starts | Spring/Summer 2021 |
Construction Complete | Summer/Fall 2021 |
Project Contacts
Town Engineer
Lee Mann (Stantec)
651-775-5956
Design Engineer
Kellie Schlegel (Stantec)
651-775-5622
Design Engineer
Joe Pond (Stantec)
612-712-2112
Construction Manager
Ryan Marquette (Stantec)
612-413-6202
Town Chair
Theresa Johnson
715-222-6235